Eric holm – The Oracle https://gunnoracle.com Official Student Newspaper of Henry M. Gunn High School Thu, 05 Sep 2024 04:48:35 +0000 en-US hourly 1 https://wordpress.org/?v=6.6.2 New administration, food services building slated to open in January https://gunnoracle.com/27540/news/new-administration-food-services-building-slated-to-open-in-january/ https://gunnoracle.com/27540/news/new-administration-food-services-building-slated-to-open-in-january/#respond Sat, 24 Aug 2024 06:39:35 +0000 https://gunnoracle.com/?p=27540 With interior wall finishes, ducts, ceilings, lighting, exterior stucco, glazing, and landscaping installations progressing during the summer, phase one of Gunn’s construction project is projected to be completed in January, with the A- and B-buildings fully in use. The construction crew will move towards the final stages that include department approvals.

Starting in January 2025 and finishing in fall 2025, phase two — which is to convert the culinary classrooms in the K-building into two Science Labs — will start after the full completion of phase one and finish in fall 2025. This construction plan that began in the fall of 2022 included a major modernization of the administration office, cafeteria and exterior and interior dining halls. The A-building will house administration facilities, a nurse’s office, a multi-purpose room for teacher meetings and additional eating areas. The B-building will feature a Design Studio and classrooms and a kitchen for Culinary Arts.

With the new administration office’s “court- yard-like entrance”, Senior Construction Manager Mohammed Sedqi explains that its location was most suitable for parents’ and visitors’ way finding and staffs’ supervision.

“The best architecture is when you don’t need a sign saying ‘admin is there’. You want to just arrive at the parking lot and clearly know where it is,” he said. “The entrance is facing the parking lot, so it’s this new face to the school entrance that helps promote the sense of place at the school.”

The renovation work includes adding 8,000 square feet to the existing 12,000 square feet of building. During the process, the crew tackled challenges with remodeling an existing building, such as the absence of utilities lines
underground and older, incorrect spokes. Sedqi also said that potential setbacks in regulatory food space checkpoints will not be a major problem, ensuring a timely debut.

PAUSD Facilities & Construction Director Eric Holm describes that many tasks, including installations of electrical wiring, landscaping and planters, were allocated to start between the end of school and start of summer school to
prevent disruption during the school year. The construction team planned to repave the streets and repaint the main exit when summer school ended on July 19.

“We try to have the least amount of disturbance to students, so we use the summer to work outside of the fences of the building construction site,” he said. “So to connect the entire power of the buildings, we had to shut down the entire campus for three days.”

Sedqi expresses a similar sentiment.

“Because of the first winter storm that hit us hard, we had a challenging period with a mud pit in construction for months,” he said. “Otherwise, summer is when we make a lot of progress without things that hit a delay like interrupting school activity.”

Holm explains that unexpected changes and additions from the original plan range from environmental concern to improved technology.

“An example is that the contractor’s access to get things would end up damaging the trees because the building was too close, so we’ve made some modifications there,” he said. “We’ve also changed as a district. Gunn is one of our test cases for a new security system and camera system inside, so that all the doors are Access Reader on this building, and you won’t need any keys to get into the building.”

For future projects, Gunn may consider cross-laminated timber, a material built from sustainably harvested big wood lumber, as used in rebuilding Herbert Hoover Elementary School in March of 2024.

“The cool thing about mass timber, which is cross laminated timber, is it being the new zero carbon footprint technology,” Sedqi said. “It’s a really good direction, and if that is successful, that might be a prototype for future projects.”

For Sedqi, whose role in construction stemmed from a childhood of building Legos, he finds it rewarding to be able to connect with students and teachers, like food services and CTE Instructional Lead and culinary science teacher Cindy Peters, to execute campus facilities or that elevate each part of the community.

“I’m proud of the culinary classroom and kitchen because I have had a lot of meetings with Cindy. If you’ve been to her class, she’s been there for roughly 20 to 30 years and it’s outdated. So I like when she’s on site and says, ‘I’m happy about this. I want to teach here.’” he said. “It’s for her and for all the students. You’re gonna get some place that is
like cooking in a place that looks like a five star restaurant. It feels really good.”

While construction is continual with interior design efforts such as installing flooring, ceiling lights and kitchen equipment; painting the walls; and putting in attack panels, Assistant Principal of Facilities Dr. Mycal Hixon points out that the administration is focused on finding ways to better students’
environments and fulfill their needs.

“It allows us to continue to support students in the best, most efficient and safest way possible,” he said. “It finally allows for a cafeteria dining space during rainy day weather and is air conditioned for students to have lunch. That definitely means a lot for Gunn, while meeting all the measures and safety disciplines as best as administration
can.”

]]>
https://gunnoracle.com/27540/news/new-administration-food-services-building-slated-to-open-in-january/feed/ 0
The cost of construction: Why it takes $1.4 million to build a classroom https://gunnoracle.com/27336/in-depth/the-cost-of-construction-why-it-takes-1-4-million-to-build-a-classroom/ https://gunnoracle.com/27336/in-depth/the-cost-of-construction-why-it-takes-1-4-million-to-build-a-classroom/#respond Mon, 20 May 2024 05:22:22 +0000 https://gunnoracle.com/?p=27336 Starting with a simple sketch on paper, the demolition and reconstruction sites of the administrative, food services and K- buildings, which first began in the fall of 2022, is now a prominent part of Gunn campus. There are, however, many aspects of construction that are often overlooked behind the sights and sounds of drilling and assembling, including months of planning, budgeting and adapting to the rising expenses.

Just like the typical grocery store item that has increased in price, inflation has triggered a rise in construction costs in Palo Alto. According to PAUSD Facilities and Construction Director Eric Holm, each square foot of commercial construction costs $700 to $1100. Additional soft costs for aspects of renovations and constructions such as designs, furniture planning and permit fees can add more than 30 to the construction’s non-interior costs. Classrooms range from 900 to 1,100 square feet, and the average cost of building a classroom has increased from $750,000 to $1.5 million in the last ten years, with projections estimating the total cost to reach around $2 million by 2028. In PAUSD, construction receives its budget from government bonds which are proposed, voted on and authorized by members of the Bond Citizens’ Oversight committee. According to the PAUSD website, The Measure A Strong Schools Bond and Measure Z Strong Schools Bond, approved by Palo Alto voters in 2008 and 2018 respectively, authorized $378 million and $460 million respectively for the district’s construction use. The amount requested is calculated with potential price growth in mind, and is utilized towards improvement in the district.

While supply chain and worker shortages due to COVID-19 have factored into this price increase, according to Holm, one of the main contributors to the total cost is the safety requirements that must be incorporated into every classroom. School buildings are considered tier two emergency services buildings, second only to hospitals, fire departments and other health care facilities. This status makes the school building’s safety and accessibility a priority. “In an earthquake or natural disaster, those buildings are the most critical, but just a hair below (them are) schools,” Holm said. “The state mandates parents to send their kids to school, (so the district) has to make the school safe for kids.” PAUSD is responsible for following certain mandates that ensure student safety. School buildings are under
the authority of the Division of the State Architect, which operates under strict structural and accessibility requirements such as compliance with the American Disabilities Act, the installation of fire safety devices and air filtration.

The construction team goes through many inspections to make sure they are following regulations. According to Hixon, these examinations have not interfered or slowed down the project’s progress.

“We adhere to all state and city guidelines for construction safety,” he said. “The experience has been great so far.”

The necessity of modern technology is another large cost in classroom construction projects. As classrooms continue
to modernize, they need to be equipped with the best materials. While it is an expense, digital projection boards and enhanced audio systems are essential to supporting teacher and student education experiences.

“Just putting a whiteboard up on the wall is a lot cheaper than putting a massive 72-inch or 60-inch TV and having all the controls to run it,” Holm said. “But all of that improves the educational experience.”

As parts of a building become detrimental to student safety, they must be replaced or repaired. These upgrades include gas phase- outs, electrical service upgrades, repairing aging infrastructure, installing air filtration and temperature control technology.

The new A-B-K building has an estimated budget of $27.5 million and includes even more extensive and specialized technology than Gunn’s other recent buildings, specifically food related technology. The project includes a complete renovation of the administrative building, as well as new food services facilities and a culinary arts classroom. Holm says that the large scope of the project contributes to its hefty price.

“The two factors (considered) are the size of the space and the number of modifications,” Holm said. “Similar to a house, a big house costs less on a per square foot basis than a small house because the base costs of construction are amortized over the entire space. A small kitchen or bathroom build or renovation will cost significantly more on a per square foot basis than a bedroom modification.”

According to Holm, general classrooms are the least expensive, followed by specialty classrooms such as art and music. This is because they are typically larger and have specialized modifications and casework. A step above are the Career Technical Education and science classrooms as they require extensive customization and equipment such as gas filtration systems. Administrative offices tend to cost even more due to the large number of interior walls and specialized spaces. Finally, highly specialized spaces like food service are the most expensive. This is reflected in the construction of the A-B-K building, as the food service section is the most expensive per square foot due to the required installation of stoves, filtration and other pieces of technology required for cooking.

A common misconception, especially about specialized classrooms, Holm noted, is the size of each classroom.Rather than a bedroom or living space, classrooms tend to be the size of a small house or apartment.

“A classroom is 1000 square feet,” he said. “That’s the  size of a small house. A 900 square foot house is selling for $1.8 million (in Palo Alto). So, by that metric, (a small) house is the same size (as a) classroom.”

Many displaced classes have relocated to portable classrooms — a part of Gunn’s campus known as the Village
— including history and less lab-based sciences that do not rely on any underground resources, such as gas lines, to run their classes. However, despite portables being almost 40% the price of a classroom, they are only temporary solutions. “A relocatable classroom is designed to be used on a temporary basis,” Holm said. “Their general life is about 20 years. They might be used longer than 20 years, but not without having problems.”

Problems may involve a leak or general wear-and-tear of materials. Portable classrooms, which can range from $50 to $150 per square foot, have thinner walls and different logistics for heating and cooling. In contrast to a physical classroom where everything is designed to circulate air in a balanced manner, portables occasionally have issues with temperature regulation, especially when smaller units are stacked together.

“The roofing is not as robust,” Holm said. “They’re not as waterproof, (and) the windows aren’t as nice. They’re a cheaper building, but then there’s a whole bunch of ways about how you install them. That changes the cost too, if they’re on a concrete foundation (versus on) a wood foundation.”

Another contributor to the cost of facilities are the constant upgrades required to ensure safety. Holm noted that if a construction team doesn’t update an establishment after it is built, they are not obligated to keep making changes. However, once they do, they must keep updating it and the other buildings around it, whether it means smartboards, alarms, HVAC systems or full renovations.

Member of the Gunn Facilities Committee Laurie Pennington says that need, impact and safety are taken into account to determine the priority of construction projects, which then determines the typical order in which projects are carried through and how they allocate funds.

“The front office building for instance, was one of the oldest buildings on campus,” she said. “It had no ventilation whatsoever. It wasn’t going to be possible just to put ventilation in that building (since) the walls were old and everything was bad.”

With the constant need to improve the quality of buildings and equipment, Holm believes that a major aspect of a successful construction project is finding an optimal time frame for each project.

“We can do a mid-year (transfer), but that’s really stressful for the teachers and students because the new room is not set up,” he said. “In a history class, (teachers might put up) historical posters, or literary (posters in an English class).(And if classes are moved,) a lot of those teacher touches are kind of invisible.”

Pennington realized that her years of experience at Gunn has allowed her to help make decisions about temporary classrooms and lodgings, which have been useful for minimizing disruption in the past.

“I’ve been here a long time,” she said. “I said, ‘If Culinary Arts is going to move out, why don’t we just put (them) back to the science (building) because all the gas is still all underneath there?’ And they hadn’t thought about that. So, it’s nice to have people that have been around for a while or people that are concerned about different departments.”

Construction has proven itself to be a far more complex process than just slotting bricks together. It takes months of planning, pitching and budgeting to finally spur a project into action. While a large part of construction cost has to do with the economy itself, directors and committees continue to strategize effective financial resource utilizations when it comes to a project that requires such a large sum of money.

Having observed the campus construction since she moved to Gunn, Principal Dr. Wendy Stratton feels the A-B-K project, set to end in December, has been worth all the time and resources and is grateful for the construction team and their work.

“I have a lot of confidence in our construction team,” Stratton said. “They’ve been really good about being communicative and inclusive. I’m really looking forward to the move and the energy that move will bring and that feeling of new beginnings.”

]]>
https://gunnoracle.com/27336/in-depth/the-cost-of-construction-why-it-takes-1-4-million-to-build-a-classroom/feed/ 0
Breaking News: Gunn community navigates water-line break, water-supply shutdown https://gunnoracle.com/27191/uncategorized/breaking-news-gunn-community-navigates-water-line-break-water-supply-shutdown/ https://gunnoracle.com/27191/uncategorized/breaking-news-gunn-community-navigates-water-line-break-water-supply-shutdown/#respond Thu, 18 Apr 2024 23:59:00 +0000 https://gunnoracle.com/?p=27191 At 11:24 a.m. today, Assistant Principal of Facilities Dr. Mycal Hixon sent a message to all Gunn staff that the school’s water had been shut off after the A- and B-building construction team hit a water line during  excavation. School remained open during the outage, and the water was turned back on at 1:30 p.m.

According to Senior Construction Project Manager Mohammed Sedqi, workers were connecting the overflow for bioswales, or runoff channels, with a storm drain when they hit the main water line. To fix the leak, workers had to first drain out the water in the pipes and then put a patch over the break. After the pipes were “purged” of air bubbles, the line was functional again. 

During lunch on the Senior Quad, staff distributed water bottles. (Eanam Maor)

Junior Hannah Kim realized the water supply had been shut off following a trip to the restroom during her Advanced Placement Statistics class. 

“Me and my friend went to the bathroom and we realized that some of the water in the toilets looked a little unclear, so we tried flushing them and they didn’t flush,” she said. 

By 12 p.m., three portable toilets had been placed near Spangenberg Theater and water bottles had been placed in the lunch lines in front of the Student Activities Center. According to PAUSD Director of Facilities and Construction Eric Holm, district officials picked up hand sinks from Fletcher Middle School and water from Costco for students to use. Thirty more portable toilets were ordered, but only arrived once the water had been turned on again. 

Students gather around a spout near the C-building as it expels water to “purge” air bubbles from the water supply. (Amann Mahajan)

Around 1:30 p.m., water spouts on building walls turned on, and toilets around campus were flushed. According to PAUSD Maintenance Supervisor Ken Culp, this preliminary reopening of the water supply “purged” the emptied water lines of air, preventing the formation of air bubbles when students and staff finally used the facilities. Following this “purge,” the water lines were fully operational, and an announcement at 1:37 p.m. notified students that the water was back on. 

The restoration process took a little over two hours in total, occurring much more rapidly than in September 2021, when the main water line was hit during parking-lot construction. Holm noted that this project’s contractors, Sausal Corporation, were more prepared to deal with the situation than Redgwick Corporation, the contractor used for the parking-lot project: In 2021, students were sent home from school early while the construction team attempted to address the issue. 

Nevertheless, students — including sophomore Rayla Chen — found the line break frustrating. 

“I just walked into the building bathroom during second period, and then all of a sudden, it said ‘out of order,’ and I didn’t know where else to go to go use the bathroom or fill up my water bottle, so that was a bit of a hassle,” she said. 

Moving forward, construction will continue as planned. According to PAUSD Operations Supervisor Brett Larson, preventative action is not necessary. 

“This is unforeseen, and that happens from time to time, and you can’t control the unforeseen,” he said.

Written by Amann Mahajan. Additional reporting by Kaylee Cheng

]]>
https://gunnoracle.com/27191/uncategorized/breaking-news-gunn-community-navigates-water-line-break-water-supply-shutdown/feed/ 0
School-board meeting sees discussion of wellness, PAUSD Promise, Local Control and Accountability Plan https://gunnoracle.com/26820/uncategorized/school-board-meeting-sees-discussion-of-wellness-pausd-promise-local-control-and-accountability-plan/ https://gunnoracle.com/26820/uncategorized/school-board-meeting-sees-discussion-of-wellness-pausd-promise-local-control-and-accountability-plan/#respond Wed, 13 Mar 2024 02:21:59 +0000 https://gunnoracle.com/?p=26820 Feb. 27’s school-board meeting addressed the student death at Gunn and provided information concerning student wellness measures on campus. Updates were also given on initiatives such as the PAUSD Promise and the Local Control and Accountability Plan. 

Board President Jesse Ladomirak opened the meeting by making a statement about the student death at Gunn on Feb. 20. Gunn School Board Representative Chris Lee (who is also a managing editor on The Oracle) also spoke about the death. 

“There are difficult, necessary conversations we must have in our community about how to better support and protect our young people,” Ladomirak said in her statement. “We can’t avoid these conversations.”

Lee discussed the measures Gunn staff and students have taken since the student death to support students. He noted that the Gunn wellness team is working to improve and make their program more visible and accessible to students, and that The Oracle has shared resources with the student body via Instagram.

The meeting continued with El Carmelo Elementary School Principal Leonel Argumedo’s equity update concerning the PAUSD Promise. As a result of the decline in literacy performance at El Carmelo, specifically from third-grade Latino and Hispanic students, El Carmelo launched the Every Student Reads Initiative, which consists of three key components: professional development, small-group instruction and data-driven discussions. According to Argumedo, in the span of one year, Latino and Hispanic students’ scores increased by 17.1 points in the English Language Arts portion of the California Assessment of Student Performance and Progress — almost closing the gap from standard by half.

“We still have work to do, but I am excited about the growth and progress students are making, and I am proud of the dedication and effort from our teachers,” he said.

Assistant Superintendent for Secondary Education Dr. Guillermo Lopez followed with the district-wide mid-year LCAP update. The LCAP is a three-year plan for local educational agencies to create goals, plan actions and leverage resources and has three main areas of focus: high-quality teaching and learning, equity and excellence, and wellness and safety.

“One of our goals was to provide an update for 11th-grade CAASPP participation rates,” Lopez said. “This is a great improvement for us. In 2023, the rate was 95% for Paly students and 96% for Gunn students.”

After the Staff Reports, two speakers expressed concerns to the Board during Open Forum, speaking on funding for Special Education programs and SELF integration at Gunn.

Director of Facilities and Construction Eric Holm ended the meeting with a Strong School Bond Program Update. Holm shared that PAUSD elementary school classrooms will hit 25 years old, their “death” age, by 2029, meaning most buildings will need to be either replaced or updated.

]]>
https://gunnoracle.com/26820/uncategorized/school-board-meeting-sees-discussion-of-wellness-pausd-promise-local-control-and-accountability-plan/feed/ 0
Fire alarm system to be replaced following multiple false alarms https://gunnoracle.com/25966/uncategorized/fire-alarm-system-to-be-replaced-following-multiple-false-alarms/ https://gunnoracle.com/25966/uncategorized/fire-alarm-system-to-be-replaced-following-multiple-false-alarms/#respond Wed, 13 Dec 2023 03:24:25 +0000 https://gunnoracle.com/?p=25966 On Oct. 24, the PAUSD Board of Education approved a $1.59 million contract to Aram Electric for installing a new Gunn fire alarm system.

The decision comes after several false alarms in the past year, caused by the current sensors’ susceptibility to hot weather. According to Assistant Principal of Safety Dr. Mycal Hixon, the new fire alarm system is expected to be installed by August 2024.

Though it will need to be modified on a site-by-site basis, the new system will serve as the district-wide standard across all campuses, according to PAUSD Director of Facilities and Construction Eric Holm. With the current fire alarm system, the loss of power in a single building can prevent other buildings’ fire alarms from working.

“Most fire alarms are wired in series, building by building, so when you do work on a building, everything downstream of that building goes offline,” Holm said. “The new system works on building a node model so each building communicates directly with the main control panel. That way, if any building goes offline, all the other buildings can stay online.”

The new alarms will have a greater tolerance for high temperatures. According to Holm, Gunn’s heat and smoke sensors are in buildings’ warm attic spaces, so on hot days, the current sensors have falsely detected fire. The new sensors will have a higher heat index, so these false alarms will occur less frequently.

According to Hixon, the installation will primarily take place on the weekends and after school to minimize disruption of classroom time.

“We’ll make sure that we communicate (with students) because we’re updating and testing (the alarms), and we want to minimize the negative impact of this project on Gunn students,” he said.

]]>
https://gunnoracle.com/25966/uncategorized/fire-alarm-system-to-be-replaced-following-multiple-false-alarms/feed/ 0
New gender neutral locker room opens on campus https://gunnoracle.com/22959/uncategorized/new-gender-neutral-locker-room-opens-on-campus/ https://gunnoracle.com/22959/uncategorized/new-gender-neutral-locker-room-opens-on-campus/#respond Mon, 26 Sep 2022 01:53:14 +0000 https://gunnoracle.com/?p=22959 The new Bow Gym gender neutral locker room became available to students on Sept. 6 after students from the Gender and Sexuality Alliance (GSA) Club started petitioning for its installation in 2019. The construction began in June 2022 and finished at the start of September. The completed locker room includes eight changing stalls, a central bench, 20 lockers and two gender neutral bathrooms.
GSA Club President senior Charlie Ennis, who, in addition to being a member of the Palo Alto Unified School District (PAUSD) LGBTQ+ Council, is also a part of the state school bathrooms ad hoc committee, has worked alongside three other students to make gender neutral spaces more accessible. “The three of us had been working together since I was in middle school on gender neutral locker rooms for Fletcher first, then I moved to Gunn and continued working on the same things,” they said.
At Gunn, they championed for new gender neutral locker rooms, as the previous one lacked space and was in less-than-ideal condition. In 2019, the students began the process of preliminary planning. A year later, they began taking action and meeting with the council and school officials. Due to the challenges presented by the COVID-19 pandemic, construction to turn the Bow Gym snack bar into a gender neutral locker room began during the summer of 2022. Some physical education (P.E.) teachers—including Amy Anderson and Steve Ames—wanted a gender neutral locker room prior to this project but were unsure of what improvements students needed. “I wanted to make sure that our school has a safe space for all students to participate in P.E. and sports and that everybody feels comfortable [in],” Anderson said.
During Ennis’s freshman year, they reached out to the P.E. teachers to discuss gender neutral facilities available for student use. Afterwards, Ennis and the two other students joined the LGBTQ+ Council—a district wide council that is working to improve inclusivity in schools. The students have continued to advocate for expanding gender neutral facilities throughout the district while providing student perspective. They worked to make the locker room at Gunn a priority for the council in early 2020.
PAUSD School Board Vice President Jennifer DiBrienza is also a member of the LGBTQ+ Council who worked as a liaison between the Gunn students and the school board. Her involvement began in the fall of 2021. During the council meetings, DiBrienza sat down with the students, board bond advisory committee and others from the opera-
tions and management departments during LGBTQ+ Council meetings. “The students explained what was missing from the current situation and what they needed to feel safe and comfortable in the locker room,” she said. The operations departments and the bond committee toured the previous facilities with the students to identify and examine the issues. Despite difficulties in contacting the district, the council members were able to get the locker room approved by sending out a presentation pointing out different health code and American Disabilities Act (ADA) violations to school board members and Gunn administrators.

A student, who asked to remain anonymous, was also part of the council and involved in the new locker room’s creation. “I saw the bad positions and unsafe conditions the students around me were in,” they said. “There have been examples of dangerous conditions inside [the old] gender neutral locker rooms such as them being locked and filled with trash, [having] holes in the wall with exposed piping and lights that would frequently go out.”

Once the plan for the locker room was finalized at a district level, Assistant Principal of Facilities Leonel Argumedo became involved with the project. Argumedo worked alongside the district to identify a space to build the locker room. “We all agreed the snack bar in the Bow Gym was the ideal space because it was not utilized as much, had a restroom nearby and was big enough to provide us the space to grow,” he said.
The construction of the locker room began under the Maintenance Department’s jurisdiction, but due to the scope of the project, it was given to the Facilities Department in January of 2021 for overseeing. PAUSD Director of Facilities and Construction Eric Holm led the project by revising layouts, getting bids and facilitating construction. Holm toured the gender neutral facilities at Palo Alto High School (Paly) with the students from the LGBTQ+ committee to compare facilities. They identified elements of the locker room at Paly that could be integrated at Gunn’s respective facility. “The old gender neutral locker rooms were a quick fix that was not really a good solution,” Holm said. “There was a strong desire to make something better and a strong need to enhance the quantity of lockers because of the large number of students that have shown an interest in using them.”
Issues arose once the construction stage of the project began. “The construction was supposed to start sooner, but because of supply challenges and shortages, [we] weren’t able to get all the materials [necessary],” Argumedo said. “The project got delayed about six months.”
Freshman Socs Kaleba has been using the new gender neutral locker room since it opened. “I really like the new locker room,” they said. “[It’s] amazing and [it] has really nice lockers. I also like how the seating area has benches for people to be able to put their shoes on.”

Alumni and former GSA President Dante Morse, who was also involved in the initial planning process, emphasized the importance of creating this comfortable space for students of all gender identities. “Creating a safe space for students to feel like they can change without having to worry about being stared at or feeling out of place is really important,” he said. “This also represents a bigger change in the ways that we’re working to include queer and trans students in our school. If we’re willing to make this kind of step to make them feel more included and we’re willing to build this room, then it shows that we’re also committed to making the school a more inclusive environment.”

Morse found that changing the stereotypical discussions and environment set around the LGBTQ+ community is crucial for creating these new spaces. “The biggest part that we had to overcome, and so many other places will have to overcome, in order to build more gender neutral locker rooms, was trying to untangle all of the stigma that exists around trans and genderqueer people,” he said.
Along with the new locker room at Gunn, the council is working towards ensuring that every secondary school in Palo Alto has a
gender neutral locker room. For elementary schools, they hope each can have at least one accessible gender neutral bathroom.

]]>
https://gunnoracle.com/22959/uncategorized/new-gender-neutral-locker-room-opens-on-campus/feed/ 0
BREAKING NEWS: School released early due to main water line break https://gunnoracle.com/21206/uncategorized/breaking-news-school-released-early-due-to-main-water-line-break/ https://gunnoracle.com/21206/uncategorized/breaking-news-school-released-early-due-to-main-water-line-break/#respond Thu, 23 Sep 2021 20:18:20 +0000 https://gunnoracle.com/?p=21206 Around 12:10 p.m. today, the administration made an announcement over the Public Address system informing students and staff that school would have an early release at 12:20 p.m. due to a break in the main water line. 

Raphael Semeria

The pipe break was a result of the parking lot construction project. While redirecting an irrigation line, workers accidentally struck the old water pipes. District Facilities Construction Director Eric Holm was on site surveying the efforts to fix the pipe break. “They were boring through this area, which is typically a less destructive method when you do water utility lines,” Holm said. “They checked the area with a ground penetrating radar, but it seems that the concrete pipe was so old that it could not be picked up by [the radar].”

According to Assistant Principal Leonel Argumedo, the admin discovered water bubbling out of the ground in the morning. Because it came from the main line, they had to shut down the water supply to the rest of the school. “There is no water anywhere,” he said. “The restrooms are inaccessible.”

In addition to the logistics of keeping 2,000 students on campus without bathrooms, the administrators were concerned about student safety. Both factored into the decision to end school early for the day. “God forbid if there was a fire,” Argumedo said. “We would have nothing to put it out.”

Construction workers on site are already working to replace the broken portion of the main line. “Right now they’re digging down to expose the line,” Holm said. “They’ve got a guy who’s already gone out to the store to buy the replacement pipes. We hope to have it finished by today.”

Jessica Wang

Even if the pipe is not fixed, administrators are optimistic of reopening the campus for class tomorrow with alternatives. Palo Alto Unified School District Superintendent Don Austin was on scene as construction workers peered into the ground. “We’re still going to be open tomorrow,” he said. “We’re going to bring portable restrooms, but obviously we don’t have that right now.”